Contacts
| Name |
Phone
|
| Msgr. Michael Howell |
(361) 387-1312 |
| Sidney Faas |
(361) 387-0797 |
| Gary Clarke |
(361) 241-3567 |
Blue Prints
Front View
Plan A: Modified Fan

Plan B: Straight Ahead
Survey Results (Dec. 3-4, 2005)
| Do you as a parishioner of St. Thomas support building a new church? |
| Yes | 171 |
| No | 14 |
| No response | 11 |
| Will you assist with fundraising? |
| Yes | 135 |
| Which floor plan do you prefer? |
Plan A
Modified Fan | 133 |
Plan B
Straight Ahead | 41 | | No preference | 21 |
|
News (July 9, 2006)
A New Church Building meeting was held on June 28, 2006. Twenty-two members of the Building Committee and Finance Council participated in the meeting.
-
Revised and discussed the bids that were received. Marshall Company was approved as the lowest responsive bidder.
-
Reviewed the total cost remaining, amount to borrow and estimated yearly income and expenses. Based on a $2,200,000 loan from the Diocese, the yearly parish expenses will be $429,000. A $2,200,000 loan is adequate to build the Church Building, furnish the Church, and provide a parking lot on the west side of the new Church. An additional $300,000 loan is required to build the Bell Tower.
-
Currently, the Diocese has approved a $2,200,000 loan. Sidney and Fr. Mike will meet with the Diocese Deposit and Loan Committee to discuss the possibility of an additional $300,000 loan. (Note: Fr. Mike and Sidney met with the Diocese Deposit and Loan Committee on July 5. The Diocese Deposit and Loan Committee did not approve the additional $300,000 loan. They suggested that the Bell Tower be built at a later date.)
-
Construction on the new Church should start within 6 weeks.
-
Sidney will discuss possible value engineering options with the Contractor and Architects and report to the Committees.
-
A list of furnishings that parishioners can contribute to is being developed.
If you have any questions, please call Fr. Mike at the Rectory, Sidney Faas (387-0797), or Gary Clarke (241-3567).
Presentations
|